Project Library

Sydney University

The Sydney College of Arts from Rozelle Campus to the Old Teachers College at University of Sydney’s main campus.
Both Buildings heritage listed
Over 3000m2 of complex equipment, machinery and assets. Print media, general workshops, jewellery, glass and sculpture and much more. Sequenced movement, placement and commissioning.
Equipment relocating includes Glass and Ceramic Kilns, Etch printing machines, wood working machinery and some very old hand built machinery.

Last minute relocation due to building structure issue – direct from the client – February 2020

Hey Steve

Just wanted to let you know that everything went well. Thank you for getting this all organized so fast.

Brooke and the guys did a fabulous job and Mark was incredible. He worked a bloody long day trying to Sort out our internet. He’s a legend and we were very grateful for his attention to detail.

Please send me the invoice.

Kind regards
Melinda

University – February 2020

Awarded 350 staff relocation from a major university – from several buildings to new purpose-built building on campus – includes academics and professors.

Major Library – January 2020

Completed packing in sequence, relocating off site and storage of 4,000 l/m. Books were cleaned and packed in total sequence Returning in April 2020. Stored in weather resistant warehouse.

APG & Co Relocation Project

Client : APG & Co

Type: Relocation

Keys: 250 Staff

Program: 14 days

Location: Sydney, Alexandria to Mascot

Date: July / August 2023

Scope of Work:

  1. Relocation externally from 11 Bowden St, Alexandria to 1
    Chalmers Crescent Mascot
  2. The relocation dates are expected to be Mid July –
    starting Saturday 15th. Have not included Sunday in our
    allowances.
  3. 3 business units – APG, Unique Retail and Apparel Group
  4. Relocation of 130 staff overall (from Level 4 and 5).

Challenges

  1. Timing and volumes. Plus, the extraction of
    products at the Alexandria site

Any Challenges:

Created a comprehensive relocation time table that outlined an hour-by-hour schedule for
completing tasks, including the coordination of
numerous clothing racks and the timelines for
I.T. disconnection and reconnection.

Tennant Company – Relocation

Project: Tennant Company – Relocation

Client : Tennant Company

Type: Relocation

Relocated: 1500 crates – 2000 pallets

Program: 10 days

Address: Eastern Creek to Horsley Park

Date: May 2023

Scope of Work:

  1. Relocation of over 50 staff including office workstations, I.T. and personal items, large warehouse of 2000 pallets – both racked and floor
    stock, pallet racking and associated equipment, packing spare parts in sequence order of 1500 crates – and assessable during the relocation period.

Challenges

  1. Sheer volumes, timing restrictions per day, client operating throughout relocation, working with the construction company as to relocate
    items in sequence as required, different unique cleaning equipment
    to relocate. Manufacture a labeling sequence that suited the client
    and the relocation process.

Solutions:

Created a comprehensive relocation timetable that outlined an hour-byhour schedule for completing tasks, the ability to change the program whilst working with Project management company, the construction company, and the client. Involving our staff heavily pre move planning, supplying enough relocation equipment without relying on returned equipment to complete, supplying expert and experienced staff. Produced labels on site to identify the products and relocation.